Crane safety measures
- Lifting equipment construction is grade four dangerous operations, belongs to the risk control object, in order to ensure safety in production, mainly to control the following aspects.
1. General requirements for safe operation
- The driver should check brakes, hook, wire rope and safety devices when to take over.
- When found the performance is not normal, that should be excluded before operation, it is not allowed to operate if the normal cannot be excluded.
- Before driving, must-ringing or alarm. When operation is near people, should give intermittent ring or alarm.
- Operation should be performed according to the command signal. For emergency stop signal, no matter who issued, it should be implemented immediately.
- When confirmation no one on or around the crane, it can be closed the main power supply. If the power disconnect device with lock or signs shall be removed before closing the main power supply.
- Before closing the main power supply, should make all controllers handle as to zero.
- Power outage in operation, all controllers handle should suddenly back to zero; before resuming work, should check whether the crane movements are normal;
- During maintenance, the driver should disconnect the main power and hang signs or lock it. If the fault is not eliminated, should notify the succession driver.
2. Safety requirements
(1) When one of the following situations occurs, the driver should not operate:
- Overloading or weight of the object is unclear. Such as lifting weights or unclear tension objects, and the oblique hanging etc.;
- Structure or component defects or injuries affecting work safety. Such as brakes, safety device failure, hook nut locking device is damaged, rope damage to be scrapped standard, etc.
- Bundling, hanging is not strong or imbalance may slide, did not add weight at the corners between the liner and the wire rope, etc.
- Someone or floating objects on the hanging object.
- Workplace is dark, unable to see the site, suspended matter and command signals, etc.
(2) The driver shall comply with the following requirements during operation:
- Do not use the limit position limiter to stop;
- Do not adjust lifting and luffing mechanism brake in the case of under load; 
- When lifting, do not hanging above people, people not allowed under the crane;
- Do not carry out inspection and maintenance work during crane operation;
- When the lifting object close to or reach the rated lifting capacity, should check brakes before lifting, and try hanging with a small height short trip, and then smoothly lifting;
- No fall limit position limiter crane, when hook at the lowest working position, the rope must remain on the roll turns according to safety design requirements.
- Mobile cranes, operating site should be flat down before work according to the specification requirement, securely and reliably lay legs;
- For non-reverse braking performance crane, except in special emergencies, not to use non-reverse braking to brake.
- With two or more cranes lifting the same object, the wire rope should be kept vertical; each crane lifting and traveling should keep pace; each crane to withstand load shall not exceed their rated lifting capacity.
- With main and auxiliary lifting mechanisms crane, main and auxiliary hook should not start at the same time. Exclude the special cranes which design allows simultaneous use.
(3) Crane general safety requirements
- Command signal should be clear, and conform to the regulations;
- When hanging, the angle between the hanging ropes should be less than 12 °, in order to avoid excessive force with hanging ropes;
- Edges and corners should be cushioned where rope and chain hit;
- When command the lifting objects flipping, should keep its center of gravity changes smoothly, should not produce action beyond the command intention;
- When entering under the suspended object, should first contact with the operator and set the supporting device;
- When people tied to hang, it needs one person responsible for the command.
3. Emergency rescue measures
- In the event of mechanical damage and injuries and other accidents in the process of lifting machinery operating, operation must stop immediately.
- If it is the mechanical damage accident, mechanical operator should immediately stop work, to keep the machinery remains in relatively safe state. Field commander should immediately evacuate construction workers of the dangerous zone. After the evacuation while not clear the cause of the mechanical accident, crane operators in ensuring their own safety before they can make a temporary mechanical safety inspection and security processing. If mechanical operators clear the cause of the accident when timely treatment should be promptly treated, if operators cannot solve the problem and need to evacuate, during evacuation should ensure the relative safety of the machinery, the commander should evacuate the construction workers in advance during evacuation to avoid other injuries. If the machinery cannot evacuate the site, should immediately set up warning area and security warning signs, and sent professionals to the security guard, prevent other personnel on-site and notify maintenance personnel for mechanical maintenance on site.
- In the event of personnel casualties, field operations should be stopped immediately, closed and guard the site, evacuate personnel. Field commanders should notify emergency rescue teams, emergency rescue immediately. If with serious injuries should be immediately sent to the nearby hospital.



Weihua Crane is professional material handling equipment manufacturer and servicer with largest production in global. Provide you with overhead crane, gantry crane, electric hoist, etc. of safe, reliable and efficient crane solutions and services.

Contact Us

Simply complete the form below, click submit, you will get the price list and wo will contact you within one business day. Please also feel free to contact us by email or phone.

Click image to refresh

Weihua Cranes Machinery Co., Ltd.

Weihua Crane standard
Weihua Cranes started since the year 1988; it is professional material handling equipment manufacturer and servicer with largest production all over the world. With Weihua Cranes historical influence, “China Crane Town” (which covers more than 2/3 crane market in China) developed in the area around Weihua Cranes headquarter.
Weihua Cranes main businesses are researching, developing, manufacturing and sales of all kinds of lifting equipment. We have passed the ISO9001 quality system certification, ISO14001 environmental management system certification, OHSAS18001 occupational health and safety management system certification, CE certification, etc.
Weihua Cranes advantages and differences with other crane manufacturers are that we have professional crane team to provide you with safe, reliable, efficient crane solutions and services, and as far as possible to reduce your cost. Crane your business, let’s develop together!

 

Excellent Product and Solutions

Weihua Cranes become one of general hoisting machinery manufacturing industry leader with the largest production and sales volume. We can provide electric hoists, single/double beam overhead cranes, gantry cranes, and such varieties of lifting equipment 10 serious more than 200 types. The lifting capacity of the overhead crane can achieve 1000t, and the gantry crane 900t, to meet all kinds of project need.
Weihua 
Cranes is committed to provide total optimized crane program solution and perfect service to help customer to save cost and improve efficiency.



 

Advanced R&D | Strong Q&C | Production capacity

Weihua Cranes has Technology Testing and Inspection Center authorized by the state, post-doctoral research station, obtains 283 technology patent certificates and inventions, R & D team of Weihua with 600 people and with Shu-zi Yang (academician from the Chinese Academy of Engineering) as the foregoer, is the biggest one in general purpose crane industry in China.
Weihua 
Cranes now adopted the “lean production management”, the undaunted testing and outstanding market performance, ensuring Weihua Cranes stand out as the leading brand within crane industry. Weihua Cranes continuously make the innovation on technical and strict on QC management to keep the products quality steady improving.

Weihua Cranes total asset is of 0.78 billion US Dollar, over 6000 employees, covers an area of 3.42 million square meters, one of Weihua Cranes workshop is the largest within the whole world crane industry. A varieties of 1700 sets manufacturing and testing equipment, including machining, heat treatment, welding, assembly, testing and packaging shipped metering and other ancillary equipment with a full range of advanced production scale and production capacity.
 

Outstanding Marketing Performance & Long-term Partner

Production and sales of overhead and gantry cranes won the first in China for continuous 8 years. And now, total production amount of Weihua Cranes products achieve world first. Weihua Cranes has developed strategic partnership with Siemens, GH Spain, Demag, SEW, Schneider, etc.

Weihua Cranes are widely used in machinery manufacturing, iron and steel metallurgy, nuclear industry of mining, water conservancy and hydropower, roads and railways, electric power, automobile manufacturing, petrochemical, port logistics, shipbuilding and other material handling, etc. We have successfully exported to more than 90 countries and regions such as the United States, Great Britain, Russia, India, Brazil, Peru, South Africa, Mongolia, South Korea, Australia, Southeast Asia, the Mid-East, etc. And get well reputation.
Weihua Cranes with strong capacity, focus on customer service, provide with first-class quality, safety and reliable products, create more and more value for customers, these are the reasons we set-up stable and long-term relationship with our customers.

 

Weihua Crane Make the World Easier | Craneus